§ 250.177. What additional requirements may the Regional Supervisor order for a suspension?
198 words·~1 min read·
/us/cfr/t30/s§ 250.177·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If BSEE grants or directs a suspension under paragraph § 250.172(b), the Regional Supervisor may require you to:
(a)Conduct a site-specific study.
(1)The Regional Supervisor must approve or prescribe the scope for any site-specific study that you perform.
(2)The study must evaluate the cause of the hazard, the potential damage, and the available mitigation measures.
(3)You must pay for the study unless you request, and the Regional Supervisor agrees to arrange, payment by another party.
(4)You must furnish copies and results of the study to the Regional Supervisor.
(5)BSEE will make the results available to other interested parties and to the public.
(6)The Regional Supervisor will use the results of the study and any other information that becomes available:
(i)To decide if the suspension can be lifted; and
(ii)To determine any actions that you must take to mitigate or avoid any damage to the environment, life, or property.
(b)Submit a revised Exploration Plan (including any required mitigating measures);
(c)Submit a revised Development and Production Plan (including any required mitigating measures); or
(d)Submit a revised Development Operations Coordination Document according to 30 CFR part 550, subpart B.
Connections1 off-index
1 reference not yet in our index
- 30 CFR 550
Citation graph
cites case law
§ 250.177
What additional requirements may the Regional Supervisor order for a suspension?
Cite30 CFR 550
Cites 1Cited by 0 across 0 sources